Nvidia weighs billions in credit guarantees for Nscale data center backing Anthropic deal
Nvidia is in discussions to back billions of dollars in debt for cloud provider Nscale to finance a 460-megawatt data center in West Virginia, according to a report by The Information.

Nvidia is negotiating billions of dollars in credit guarantees to help cloud provider Nscale finance debt for a planned 460-megawatt data center in West Virginia, according to a report by The Information. The infrastructure project is tied to a $45 billion compute agreement between Nscale and artificial intelligence startup Anthropic, which plans to utilize the facility.[5][3][2][4][1]
The credit backing could exceed $5 billion based on industry estimates cited in the report. Rather than funding chip acquisitions, the guarantees would cover power and construction expenses for the facility, which is expected to deploy Nvidia's Vera Rubin GPUs. The agreement has not yet been finalized, and terms remain subject to change.[5][1]
Key facts
- Nvidia is in talks to provide Nscale with billions of dollars in credit guarantees to finance debt for a 460-megawatt data center.
- The planned data center is located in West Virginia and is intended for Anthropic.
- Nscale holds a $45 billion compute deal with Anthropic for the facility.
- Industry estimates indicate the credit support could exceed $5 billion.
- The credit guarantees are structured to cover power and construction costs rather than GPU purchases.
- The facility is expected to run Nvidia's Vera Rubin GPUs.
- The agreement has not been signed and its terms may change.
Sources · 4 sources
- SB
Shay Boloor@StockSavvyShayPost on X ·
$NVDA is reportedly in talks to provide over $5B in credit guarantees for Nscale's 460MW data center backed by a $45B $ANT compute contract. Nvidia would essentially be financing power and construction rather than GPUs which could help bring more Vera Rubin capacity online faster while lowering borrowing costs for its customers.
Open source - *B
*Walter Bloomberg@DeItaonePost on X ·
NVIDIA IN TALKS TO PROVIDE BILLIONS IN CREDIT SUPPORT FOR A CLOUD PROVIDER’S $45 BILLION ANTHROPIC DEAL - THE INFORMATION
Open source - TE
Techmeme@TechmemePost on X ·
Sources: Nvidia is in talks to provide Nscale with billions of dollars in credit guarantees for debt to develop a 460MW data center that Anthropic plans to use (@_pheebini / The Information) (Visit Techmeme dot com for the link and full context!)
Open source - *B
*Walter Bloomberg@DeItaonePost on X ·
NVIDIA IS IN TALKS TO PROVIDE NSCALE WITH BILLIONS IN CREDIT GUARANTEES FOR DEBT TO DEVELOP A 460-MEGAWATT DATA CENTER - THE INFORMATION
Open source - WS
Wall St Engine@wallstenginePost on X ·
$NVDA is in talks to provide Nscale with billions of dollars in credit guarantees to finance a 460MW data center in West Virginia for Anthropic. Nscale has a $45B contract with Anthropic for the facility, which is expected to use NVIDIA's Vera Rubin GPUs. The credit support could exceed $5B, based on industry estimates, and would cover power and construction costs rather than chip purchases. The agreement has not yet been signed, and terms could change. Source: The Information
Open source